Project
Task Phases
Design & Engineering 6/6  ·  15h est.
Initial site survey / load calc 2h
Hydraulic system design 4h
LoopCAD layout 3h
Control panel engineering 3h
Drawing package & submittals 2h
Engineer review & sign-off 1h
Procurement 4/4  ·  3.5h est.
Bill of materials 1h
Vendor quotes 1h
Purchase orders issued 0.5h
Receiving & inspection 1h
Fabrication 5/5  ·  16h est.
HydroPro panel build 8h
Manifold assembly 3h
BPEX tubing prep 2h
Insul-Tarp staging 1h
QC bench test 2h
Programming & Controls 4/4  ·  7h est.
Control 365 configuration 2h
GeoLink integration setup 1.5h
Zone mapping & sequences 2h
Factory acceptance test 1.5h
Field Installation 4/4  ·  20h est.
Tubing installation 8h
Equipment rough-in 6h
Panel installation & wiring 4h
System fill & purge 2h
Commissioning & Closeout 5/5  ·  6.5h est.
System startup & balancing 3h
Owner training 1h
As-built documentation 1.5h
Warranty registration 0.5h
Final invoice & closeout 0.5h
28
Tasks
6
Phases
68h
Est. Hours
Done!